IRON GATES I – REHABILITATION WORKS  OF THE NAVIGATION LOCK ON THE ROMANIAN SIDE Name of the employer : HIDROELECTRICA SA Completion period : 2006 - 2013 Contractor : Consortium made by  ROMENERGO S.A.,  ENERGOMONTAJ SA and  HIDROCONSTRUCTIA SA with ROMENERGO S.A. as leader of the consortium and DSD-NOELL (Germany) as subcontractor of ROMENERGO Scope of works: engineering & design, civil construction, supply of equipment, rehabilitation works, erection, testing, commissioning and training
REHABILITATION  WORKS  OF THE  NAVIGATION  LOCKS  ON  THE  DANUBE –BLACK  SEA  CHANNEL Name of the employer:ADMINISTRATIA  CANALELOR NAVIGABILE (ACN) Completion period : 2013 - 2020 Contractor : Consortium made by ROMENERGO S.A., DSD-NOELL GmbH, UTI SA, UTILNAVOREP SA and ARGOS SA,  with ROMENERGO S.A. as leader of the consortium. Scope of works: engineering & design, civil construction, supply of equipment, rehabilitation works, erection, testing, commissioning and training